Las Vegas, NV
Work Completed:
- Electrical
Overview:
Byers was contracted to complete the Electrical installation of a new Niagara Bottling facility in Las Vegas, NV. This project consisted of setting multiple Power Distribution panels, 480v- 240v Transformers, 240v – 120v Panels, and various Control Cabinets. Included in the project was also a complete electrical installation of the Utility, Water Process, Injection, and Processing Line Equipment. All Cable Tray, Supports, Wireway, Power and Control Wiring was completed by the Byers Team. This project also including specialty 400v equipment due to the fact the equipment being from outside of the United States. This project was completed under budget and on time.