August 27, 2025

Galvanizing Line Upgrade – Blytheville, AR

At a steel mill in Blytheville, Arkansas, Byers was contracted to execute the electrical interconnections for a galvanizing-line upgrade, including a new coating pot and premelt pot, lift system, bogie travel system, isolation transformer, water-pump modules, and control panels. The effort was organized around a planned outage, with mobilization ahead of the shutdown and continuous 24/7 work during the outage window to meet the restart date. Milestones targeted mobilization, shutdown start/finish, and final completion shortly thereafter, with pre-shutdown tasks advanced on straight time to de-risk critical path activities.

Scope included 480-V power and control wiring from the plant switchboard to the main system enclosure, hydraulic power unit, lift motors, operator stations, valve stands, and multiple junction boxes on the lift assembly; PLC-to-device control circuits for e-stops, power supplies, pot covers, alarms, drain manifolds, bath-level lasers, and water-system interfaces; and new 4.16-kV services between generator, automatic transfer switches, switchgear, transformers, and low-voltage power supplies with grounding and tray extensions/new tray as required. Additional work covered water-system feeders to control panels, pump modules, emergency solenoids, and instrumentation tie-ins, plus assistance with installing cable tray and water-cooled leads to the pots. All conduits routed through foundry areas were rigid, with tray/rigid transitions at vaults and terminations.

Execution followed the bid package and drawings with clear change-control procedures, daily coordination meetings, and testing responsibilities to streamline commissioning. The schedule provided for seven-day, 24-hour periods during the outage, with provisions to add overtime, shifts, or workdays if recovery was required. Document precedence, RFI handling, and progress controls (sign-offs, time sheets, inspections) were defined to ensure a clean, code-compliant installation and on-time turnover of the upgraded galvanizing line.

View The Rest Of The Gallery For: Galvanizing Line Upgrade – Blytheville, AR and contact us today to start your project

Rob Sebia

Chief Executive Officer

“We favorably impact people, families and communities with our work, our projects and our charitable efforts. It’s an exciting place to be every day and our opportunities to contribute will grow as we continue to grow around the United States.”